– All basement car park levels are complete.

– Ground floor transfer slab is almost complete, with the balance to be poured 15th of May.

– Precast concrete panels from ground to Level 1 started on 7 May.

– The building water fire booster pump is now fixed in place.

– Construction of Cello’s two residential towers now begins!

– CSDG construction team is ahead of our construction progress schedule, and on track for a timely completion.

THE SALES DISPLAY IS CURRENTLY OPEN WEDNESDAY TO SATURDAY 10:00 AM TO 12 :00 PM OR BY PRIVATE APPOINTMENT PLEASE CALL NICK ON 0406 992 320 TO ARRANGE A SUITABLE TIME TO MEET.

Project website – www.celloapartments.com.au

 

 

Cello Construction Update – April 2020

Cello Construction Update – April 2020 • All basement car park levels are complete.• Ground floor transfer slab is almost complete, with the balance to be poured 15th of May.• Precast concrete panels from ground to Level 1 started on 7 May.• The building water fire booster pump is now fixed in place.• Construction of Cello’s two residential towers now begins!• CSDG construction team is ahead of our construction progress schedule, and on track for a timely completion.THE SALES DISPLAY IS CURRENTLY OPEN WEDNESDAY TO SATURDAY 10:00 AM TO 12 :00 PM OR BY PRIVATE APPOINTMENT PLEASE CALL NICK ON 0406 992 320 TO ARRANGE A SUITABLE TIME TO MEET.Project website – www.celloapartments.com.au

Posted by CS Development Group on Friday, May 8, 2020