– All basement level slab pours are now complete.
– Ground floor has been formed, and is on track to be completed by end of April 2020.
– Service installations are progressing in the basements.
– Level one precast panels are on track to be installed by end of April 2020.
– Brisbane City Council re-commenced their development of the nearby Hanlon Park.
– Pool structural walls on track to be completed by April 2020.
– CSDG construction team is ahead of our construction progress schedule, and on track for a timely completion.