🚧 🏗 CSDG construction team is ahead of our construction progress schedule, and on track for a timely completion.

✅Scaffold stripping is in progress and the unveiling of Tower 1 will happen before the Xmas break.

✅Roofs on both towers are complete, work on our rooftop entertainment area is progressing well.

✅Brisbane City Council’s redevelopment of Hanlon Park is well under way with major excavation work underway.

✅Fit out of apartments on Tower 1 is in the final stages.

✅1 & 2-Bedroom displays are complete and open for inspection.

✅Our internal lifts in both towers are complete.

✅The ground floor lap pool shell has been sprayed & is ready for finishing trades in the New Year.

✅Services (plumbing, electrical, security, Air Conditioning & fire sprinklers) are almost complete with only levels 7 & 8 on Tower 2 to go.