1. The structure is now complete with level 8, concrete swimming pool shell poured last Wednesday 19/12.

2. All of the scaffolding has been removed from the northern elevation of the building and the remaining scaffold will be removed during January and early February.

3. Units on ground and first floors are completed, cleaned and locked off.

4. Three bedroom furnished display apartment is now open for inspection, A second (2 bedroom) display unit will be opened by end of January.

5. Internal wall framing, services and sheeting is complete up to level 6.

6. Internal painting completed upto Level 4 & external painting completed for the northern elevation.

7. We expect to have our elevators operational by late January.