• The main structural blockwork walls are complete to the underside of the ground floor.

• Installation of structural braces to support the basement excavation is complete.

• Soil excavation of the site is now at Basement level 2.

• Permanent concrete shotcrete of the basement walls will commence before the end of April.

• Stormwater retention basin concrete slab will be poured this week.