Construction Update [Oct – Nov 2020]

Construction Update [Oct – Nov 2020]

🚧 🏗 CSDG construction team is ahead of our construction progress schedule, and on track for a timely completion. ✅Scaffold stripping is in progress and the unveiling of Tower 1 will happen before the Xmas break. ✅Roofs on both towers are complete, work on our rooftop...

read more
Cello Construction Update  [Aug-Sept 2020]

Cello Construction Update [Aug-Sept 2020]

CSDG construction team is ahead of our construction progress schedule, and on track for a timely completion. • Tower 1 & Tower 2 have reached their full heights! • All structural aspects of Tower 1 & 2 are now complete. • Roof on Tower 1 now complete. • Tower 1...

read more
Cello Construction Update – [July 2020]

Cello Construction Update – [July 2020]

✅ CSDG construction team is ahead of our construction progress schedule, and on track for a timely completion. ✅ Level 7 in Tower 1 and Level 5 in Tower 2 have been poured. ✅ Ceiling painting work has started on the ground level. ✅ Internal fit-outs are progressing...

read more
Cello Construction Update – [June 2020]

Cello Construction Update – [June 2020]

✅ Suspended slabs poured for : Tower 1 - Levels 3&4; and Tower 2 - Levels 1&2. ✅ Next 2 levels in each tower will be finished in the next 2 weeks. ✅ Builders hoist lift is installed and operational. ✅ Removal of back-props is progressing well. ✅ Fit out for internal...

read more
Cello Construction Update – [May 2020]

Cello Construction Update – [May 2020]

- Level 1 in Tower 2 & Level 2 in Tower 1 has been poured. - Level 3 in Tower 1 is scheduled to be poured on 18th June 2020. - Precast panel installation work in both building towers is progressing well. - All mechanical exhaust equipment has been installed in the...

read more
Cello Construction Update – [April 2020]

Cello Construction Update – [April 2020]

- All basement car park levels are complete. - Ground floor transfer slab is almost complete, with the balance to be poured 15th of May. - Precast concrete panels from ground to Level 1 started on 7 May. - The building water fire booster pump is now fixed in place. -...

read more
Cello Construction Update [March 2020]

Cello Construction Update [March 2020]

- All basement level slab pours are now complete. - Ground floor has been formed, and is on track to be completed by end of April 2020. - Service installations are progressing in the basements. - Level one precast panels are on track to be installed by end of April...

read more
Cello Construction Update [February – March 2020]

Cello Construction Update [February – March 2020]

- All basement level slab pours are now complete. - Ground floor has been formed, and is on track to be completed by end of April 2020. - Service installations are progressing in the basements. - Level one precast panels are on track to be installed by end of April...

read more
Cello Construction Update – February 2020

Cello Construction Update – February 2020

We are excited to announce that our Cello project is officially above ground! Despite rainy weather conditions in the past few weeks, our construction team is running well ahead of our construction schedule! Basement Level 3 slab has been poured, Basement Level 2 slab...

read more
Construction Update January 2020

Construction Update January 2020

• Bulk excavations, reinforcement concrete, pad footings and lift pits are now complete. • Wall shotcrete is now completed. • Basement plumbing & drainage work is progressing. • Reinforced Block wall work for lower basement levels is progressing well. • Site tower...

read more