Construction Update (Hanlon Park Residences) Jan/Feb 2019

Construction Update (Hanlon Park Residences) Jan/Feb 2019

1.Building scaffolding is now dismantled to reveal a stunning facade. 2.Internal fit out is progressing well with level G, 1, 2, 3 & 4 now completed & locked off. 3.Building service connections, landscaping and pool works have been completed. 4.Parking spaces have now...

read more
Construction Update September 2/2

Construction Update September 2/2

We are pleased to advise that construction of Hanlon Park Residences is ahead of schedule and forecast to complete in April 2019. Key Updates – Level 7 was poured last week and remaining levels to be completed by the end of this month. Display apartment will be ready...

read more
Construction Update – September

Construction Update – September

Painting works started on ground level, Plaster partition walls installation on level 1 & 2 progressing really well. Display apartment - Floor tiles, kitchen benchtops & cabinets will be installed by first week of...

read more