Helia Sanctuary Construction Update [April 2022]

Helia Sanctuary Construction Update [April 2022]

• The main structural blockwork walls are complete to the underside of the ground floor. • Installation of structural braces to support the basement excavation is complete. • Soil excavation of the site is now at Basement level 2. • Permanent concrete shotcrete of the...

read more
Helia Sanctuary Construction Update [January 2022]

Helia Sanctuary Construction Update [January 2022]

Our CSDG team is powering forward with our latest project, and on track for a timely completion. • All pilling works are now complete. • The concrete capping beam for the basement retention system is now almost complete. • The west boundary retaining wall footing is...

read more
Helia Sanctuary Construction Update [August 2021]

Helia Sanctuary Construction Update [August 2021]

CSDG is proud to announce the commencement of our latest project located in West End, civil works are progressing well with new stormwater and sewer connections, concrete footing work will commence next week, stay tuned for more updates!

read more
Project Completion – Cello Apartments [June 2021]

Project Completion – Cello Apartments [June 2021]

We’re proud to announce the successful completion of Cello Apartments, Stones Corner. We’d like to thank you, the entire CSDG team, our contractors and consultants on your contribution to the success of this project. The finished building has delivered our vision of...

read more
Cello Construction Update [April 2021]

Cello Construction Update [April 2021]

 • Both swimming pools are complete.  • Fit-out of residential units has been completed.  • Feature finishes in ground floor lobbies are progressing well.  • Landscaping at ground level is nearing completion. • Main entry driveway including footpaths work is nearing...

read more
Cello Construction Update  [February – March 2021]

Cello Construction Update [February – March 2021]

Fit-out of residential units is nearing completion. Feature finishes in ground floor lobbies are progressing well. Landscaping at ground level is well underway. Both swimming pools are complete, ready to be filled! Main entry driveway including footpaths work now...

read more
Cello Construction Update – January 2021

Cello Construction Update – January 2021

Most of the scaffold has been removed from Tower 1. Scaffold removal has commenced on Tower 2. Unit internal finishes on Tower 1 will be complete by Mid-February. Unit internal finishes on Tower 2 are on track and have been completed up to level 4. Basement car...

read more
Construction Update [Oct – Nov 2020]

Construction Update [Oct – Nov 2020]

🚧 🏗 CSDG construction team is ahead of our construction progress schedule, and on track for a timely completion. ✅Scaffold stripping is in progress and the unveiling of Tower 1 will happen before the Xmas break. ✅Roofs on both towers are complete, work on our rooftop...

read more
Cello Construction Update  [Aug-Sept 2020]

Cello Construction Update [Aug-Sept 2020]

CSDG construction team is ahead of our construction progress schedule, and on track for a timely completion. • Tower 1 & Tower 2 have reached their full heights! • All structural aspects of Tower 1 & 2 are now complete. • Roof on Tower 1 now complete. • Tower 1...

read more
Cello Construction Update – [July 2020]

Cello Construction Update – [July 2020]

✅ CSDG construction team is ahead of our construction progress schedule, and on track for a timely completion. ✅ Level 7 in Tower 1 and Level 5 in Tower 2 have been poured. ✅ Ceiling painting work has started on the ground level. ✅ Internal fit-outs are progressing...

read more